Skip to content
For the complete documentation index, see llms.txt. This page is also available as Markdown.

Scheduling chemical programs (starting rounds & linked programs)

Pick the first visit and Shortcut plans the whole season — suggested starting rounds, catch-up, and linked start dates when a customer has multiple programs.

When you schedule a seasonal chemical program, Shortcut plans the whole season for you: pick the first visit's date and it fills in the remaining rounds on their planned months — and if a customer has more than one program, it lines them all up to the same start. Open Jobs →

This applies to seasonal chemical programs (rounds tied to planned months). Interval programs (e.g. mosquito every 21 days) and one-off chemical services schedule like any other service. See Chemicals for the difference.

What this does

  • Suggests the right starting round for the time of year, so a customer you sell in July doesn't start at Round 1

  • Auto-fills later rounds on their planned month and week — every visit on the same weekday as the first

  • Skips rounds that have already passed — or lets you include them anyway (a manual catch-up)

  • Links a customer's multiple programs so one start date sets them all, each landing in its own season

Where you can schedule from

The same scheduler opens from every list where a pending chemical job appears:

  • Jobs — click Schedule on the job (or select several and click Schedule in the bar that appears)

  • Dispatch — the Unscheduled tab (Schedule on the row), or Backlog in the side panel

  • Customer profile → Jobs tab → the job's ⋯ menu → Schedule…

  • Calendar → Unscheduled → Schedule

  • Estimate page → right after you approve an estimate, Schedule jobs

From the customer profile you schedule one job at a time, so programs aren't linked there. To line up several programs for the same customer, schedule them together from Dispatch or Calendar — see When a customer has multiple programs.

Schedule a program

1

Open the scheduler

Click Schedule on a pending chemical program. A calendar opens with the program's rounds listed beside it.

2

Pick the first visit date

Choose a date on the calendar. Shortcut sets that as the first visit and fills the remaining rounds automatically — each on its planned month/week, on the same weekday.

3

Check the starting round

Shortcut picks a Suggested starting round for the season (see below). To start earlier or later, click Choose starting round and pick a different round.

4

Fill any required dates

If a round needs a date you have to set yourself, its row shows Date required — this happens for catch-up rounds Shortcut can't safely auto-date, and for programs whose season has already passed. Click the round and pick a date. The running summary tells you how many are still needed.

5

Schedule

Click Schedule for these dates. (The button reads Select dates to schedule and stays disabled until every included round has a date.)

Choosing the starting round

By default Shortcut selects the Suggested round — the latest round whose window has already begun for the date you picked — and marks it with a Suggested badge. Everything before it is treated as already done and left off the schedule.

  • Start later or earlier: click Choose starting round and pick any round. Choosing an earlier round is a manual catch-up — you'll see "Manual catch-up includes [round] and every sold round after it." Any included round that can't be auto-dated will ask you for a Date required.

  • Go back to the suggestion: click Reset to suggested to drop the manual choice and return to the season default.

Scheduling after the season has ended

Late in the year, today can fall after a program's last round. When you schedule one seasonal program on its own, the window then says Selected date falls after this program's seasonal window. Choose a date in a planned service month. Under that message, click Start next season (Apr 2027) — the button names the month next season starts — and Shortcut starts the program on next year's first round, on the same weekday as the date you picked.

When a customer has multiple programs

If you schedule a customer who has more than one pending program at once (for example a fertilization program and a weed-control program), the programs are linked: the first date you choose becomes a shared start, and every program lines up to it — each one landing in its own season, not just copying the raw date.

Each program shows a small status so you can see what happened:

Status
What it means

Linked

The program picked up the shared start date and planned its season from there.

Seasonal default

The shared date falls before this program's first round, so it starts in its own first-round window instead — still on your chosen weekday.

Date required

The shared date falls after this program's last round — its season has already passed, so you need to pick a date for it before scheduling.

Edited

You changed this program's date or round yourself. It's now independent — it keeps your choice and won't move when you change the shared date.

You'll also see a one-line summary per program, like "Round 4 starts Mon 08/12," so you can confirm each one at a glance.

Two of a customer's programs in the scheduler after a shared start of Tue 04/13: Broadleaf Weed Control Program with the blue Linked badge and Round 1 starts Tue, 04/13, and Grub & Insect Program with the amber Seasonal default badge and Round 1 starts Tue, 06/01
One program picks up the shared date (Linked); the other waits for its own first round (Seasonal default).

Skip a round this year

Sometimes one application should sit out a season, for example no crabgrass pre-emergent the year a customer overseeds. Skip that round for this year. It isn't done or charged this season, and it's due again next year. The customer gets no message.

  1. Find the scheduled program on the Jobs page, or under Current jobs on the customer's profile.

  2. Click ⋯ → Skip this year….

  3. Tick each round to skip. Each round shows what it's doing now: Not booked, Booked May 10, Under way or Done May 10. Rounds that are done or under way can't be ticked. To skip the whole program, tick every round.

  4. If the program has more than one season to pick from, choose it under Season.

  5. Click Save.

The Skip this year: 6-Step Lawn Care Program window with 2027 season chosen, Round 1 ticked and marked Skipped for 2027, and the other five rounds Not booked
Tick the rounds to skip for the season, then Save.

The job shows a pill such as Round 1 skipped for 2027. To list every program with a skipped round, set the Jobs Status filter to Skipped this year.

Changed your mind? Open Skip this year… again, untick the round and click Save. The round is due again in Dispatch, where you book it.

Skip this year… is offered for seasonal programs that are already scheduled. A round skipped on the estimate carries over to the job. See Pause, resume, or cancel a job for other ways to stop work.

Good to know

  • The running summary counts how many visits are included, how many earlier rounds were skipped, and how many still need a date — it updates as you make changes.

  • Sold rounds, current mix: the rounds and their dates stay as they were sold to that customer. The products and rates on each round that hasn't been recorded yet follow the program as it is now in Chemicals. See What your edits change on jobs you've already sold.

  • Programs keep their own season. A chemical program's rounds already follow its season, so programs don't take a service season and are left out of Pause for season.

  • Starting next season: a program booked to start next year isn't flagged Chemical due in Dispatch before its season begins.

Still stuck?

Email hello@shortcutco.com with the customer name, the program, and the date you're trying to start on — a screenshot of the scheduler helps.

Last updated