Closeout and cancelling a project
Finish a project: review the actuals, clear the gates, close out with the final invoice, start the warranty, collect retainage, and close. Or stop a project early and settle on the work done.
A project is finished in two steps. Close out happens when the work is done: you check the actuals against the estimate, clear anything still open, and send the final invoice; it starts the warranty and the retainage clock. Close project happens when the money is in: nothing is owed, every payment is settled, and the project goes to Closed.
The Closeout tab
A project lands on Projects → Closeout when every phase is reviewed or done (or the last one is on a punch list) and no change order is left waiting. Each row shows the Closeout step, any Unbilled work, the Final invoice (Not invoiced yet, Draft · $5,060, INV-1009 · $3,475 · Due Nov 22, Paid Oct 3), the Realized margin against the sold one (red when it's more than 5 points under), and the PM. The row's button is the next step:
Punch list open
The last phase was sent back; 2 of 2 left · Install A Wed.
Punch list
Ready to close out
Everything is reviewed.
Close out
Final invoice draft
Closed out; the final invoice is a draft.
Send invoice
Final invoice sent / Awaiting payment
The customer has it; Due Nov 22 or Overdue.
Resend / Remind
Retainage held
The final is paid; retainage is due later, Held · $499.64.
—
Paid in full
Nothing owed.
Close project
Closed
Done.
—
A note at the bottom says it: Close a project yourself once nothing is owed – a payment never closes it for you, and a reversed payment reopens the amount owed, not the work.

Close out
Click Close out (the project's main button, or the row on the Closeout tab). The Close out: [project] window is the project's report card:
Sold, Change orders, Final contract, and the Realized margin against the sold margin (↓ 2.1 pts vs sold 45.9 %), with the labor, materials, and equipment behind it.
Actual vs budget — per phase: Hours · est / actual, Materials · est / actual, Equipment · other, the Phase margin, and Why over (the reason the crew or you gave, or On budget).
Materials — every item with what was Used, Returned to the yard (type it here; it takes the cost off the phase), Billed, and the Cost on the job.
Before you close — the gates. All phases reviewed, Punch list (the open items, with Done with photo, Can't do, Edit, and Add an item; Punch list done opens once every item is done or marked can't do), Change orders signed, and Nothing unbilled (Every hour, material and change order is on an invoice, or Add to final invoice). Each has a fix beside it. Lien waiver received is a reminder only; it never holds the closeout.
Draft the final invoice for [name] — ticked by default, with the balance it will bill (Balance $841.62 · before tax · stays a draft until you send it). When nothing is due, the tick creates no invoice.
Click Close out & draft final invoice. The actuals lock, the closeout date is set, the warranty starts, retainage (if any) gets its due date, and the final invoice waits as a draft under Documents. Send it from the invoice when it reads right.

The final invoice
The final invoice bills what's left of the payment schedule (the Balance), plus any time-and-materials work and next-invoice change orders not yet billed, minus credits carried forward. It shows the customer every payment received, the contract (the signed estimate and each signed change order), and the warranty line. From then on it's an ordinary invoice: reminders, partial payments, receipts, and QuickBooks all work the same way. See Review, progress payments, and invoices.
The Closeout section on the project
After closeout the project page's Closeout section carries the record: Closed out (the date), Warranty (12 months · until Oct 23, 2027), Retainage ($499.64 · upcoming · due Nov 21, with Waive), Lien waiver (Not received yet or Received Oct 30, with its tick), and the list of what's still in the way of closing, each with its action:
Balance (invoiced, unpaid) is not settled. / The customer still owes $1,737.52. — wait, or Remind from the invoice.
Retainage (upcoming) is not settled. — it bills on its due date, or Waive it (The $499.64 retainage is waived: it never bills and the project earns that much less.).
Unbilled work — tick the rows and Add to final invoice, or Write off them with a reason.
A draft invoice is waiting to be sent or voided., A payment is still processing., A refund is still pending., A payment is disputed. — settle it on the invoice.
An invoice or refund didn't go through; retry it below. — Retry on the line.
Retainage
Retainage is a slice of the contract the customer holds back until some days after closeout, so they know the work will stand. You set it on the payment schedule when you mark the project approved (Days after closeout (retainage)), or the customer signs a schedule that includes it. It shows as its own step: Retainage · due in n days on the Closeout tab and Retainage · $499.64 · upcoming · due Nov 21 on the project. On the due date Shortcut sends the retainage invoice on its own. If you'd rather not bill it, Waive it. A project can't close while retainage is upcoming.
Closing the project
When nothing is owed, every payment is settled, and no invoice is a draft, the Closeout step reads Paid in full and the main button is Close project. Click it and confirm. Shortcut runs the final settlement: it checks what was invoiced against what the project earned, and if a credit was carried forward it issues a credit memo on the last paid invoice and refunds the difference. The section then reads Final settlement complete., the badge reads Closed · paid in full Sep 4, and the stats switch to Final contract, Paid, Hours, and Realized margin. A settlement line that fails shows under Final settlement with Retry.
After closing
Create follow-up estimate — a new draft for the same customer.
Reopen — adds a warranty phase so the crew can be scheduled back. The warranty window and the paid invoices stay as they are. See Rework and warranty work.
Archive — hides the project from the Closeout and All lists unless Show archived is on. Nothing else changes.
A payment reversed later doesn't reopen the work: the waiting box reads A payment was reversed. The customer owes it again. with Request payment, which sends a reversal invoice for that amount. The original invoice stays paid.
Reopen a phase
A reviewed phase that turns out to need another visit can be reopened without reopening the project. On the phase's ⋯ menu choose Reopen as punch list: give the Reason for reopening and the Punch list items, one per line, and click Reopen phase. The phase goes back to In progress with the punch list, and the frozen totals are kept. Warranty or rework phase on the same menu adds an unbilled phase instead.
Cancelling a project
A project that stops after approval is cancelled, not deleted, so the work done so far is still recorded and billed fairly. Open the main button's arrow and choose Cancel project.
Why is it stopping? — Customer cancelled, Site or permit issue, Payment problem, We can't do it, or Other (with a note).
Work done so far — how to settle: Bill work to date (each phase earns by its own rule: a reviewed fixed phase its price, a phase in progress its price × declared %, a T&M phase its hours and materials), a Custom amount before tax, or Don't bill.
The settlement preview — the earned amount per phase (Wall · 70% declared · $6,977.00), tax, Paid so far (deposit), and the result: Final invoice to [name] or Refund to [name].
What happens next — the team's days are released on Dispatch and the team app shows Project cancelled; open change orders are voided; upcoming milestone invoices are dropped; the settlement invoice, credit, or refund goes out; and the project moves to Cancelled with its actuals and margin still recorded. It can't be reopened; duplicate it instead.
A change order the crew worked on but the customer never signed has to be resolved first (Bill the hours as T&M or Keep as internal rework (no charge)). Click Cancel project to confirm, or Keep project.

The settlement runs once every payment has cleared (an ACH payment still processing holds it). Each line (an invoice voided, a credit memo, a refund, a settlement invoice) shows under Settlement on the project page with its state, and the section reads Cancellation settlement complete. when it's done.
Last updated